Questions # 81:

Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

Question # 81

Based on the network diagram, find out which path is the critical path for this project?

Options:

A.

ABEHJ


B.

ABDIJ


C.

ABDHJ


D.

ACFIJ


Expert Solution
Questions # 82:

There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

Options:

A.

Scope baseline


B.

Activity attributes


C.

Activity list


D.

Activity resource requirements


Expert Solution
Questions # 83:

You work as a Project Manager for Tech Perfect Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

Question # 83

What will be the cost variance (CV) of the project at the current point of time?

Options:

A.

+80


B.

-80


C.

-10


D.

+10


Expert Solution
Questions # 84:

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

Options:

A.

-$98,217.78


B.

-$44,198


C.

$441,025.64


D.

$243,219.78


Expert Solution
Questions # 85:

You are the project manager of the NHQ Project. This project has a Budget at Completion of $750,000 and is expected to take 18 months to complete. The project is supposed to be 75 percent complete, but due to some errors the project is only 60 percent complete. At this time the project has spent $465,500. Management has asked you to review the project work and report the project's SPI. What is the SPI for this project?

Options:

A.

0.97


B.

0.80


C.

$562,500


D.

-$112,500


Expert Solution
Questions # 86:

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project Management process are you working with when you create a new target schedule?

Options:

A.

Develop schedule


B.

Estimate activity durations


C.

Control schedule


D.

Estimate activity resources


Expert Solution
Questions # 87:

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

Options:

A.

Resource competition


B.

Matrix organization


C.

Resource requirement


D.

Resource constraint


Expert Solution
Questions # 88:

You are the project manager of the NGG Project. This project will be using a new material that the project team has never worked with before. You'd like to use some preventive action to ensure that the installation of the new materials is successful in the project. Which one of the following project actions is an example of the best preventive action for this project?

Options:

A.

Hire a subject matter expert to train the project team how to install the materials.


B.

Purchase additional materials so in case the team wastes materials during their installation.


C.

Hire a subject matter expert to install the new materials.


D.

Create incentive by rewarding the project team if they don't waste the materials.


Expert Solution
Questions # 89:

You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

Options:

A.

Project Schedule Management Plan


B.

Project Staffing Management Plan


C.

Project Human Resources Management Plan


D.

Project Communications Management Plan


Expert Solution
Questions # 90:

You are the project manager for GGY Project. You are working with your project team to record the actual durations for the activities they have completed in the project schedule. Mary, one of your project team members, wants to know why you need to know how long it actually took the project team to complete their assignments as long as the project work is completed. Which of the following is the best response for Mary's query?

Options:

A.

Actual durations need to be recorded to track process improvement.


B.

Actual durations need to be recorded to create the schedule baseline.


C.

Actual durations need to be recorded to measure the actual progress of the project.


D.

Actual durations need to be recorded to perform quality control on the project management processes.


Expert Solution