PMI Scheduling Professional PMI-SP Question # 86 Topic 9 Discussion

PMI Scheduling Professional PMI-SP Question # 86 Topic 9 Discussion

PMI-SP Exam Topic 9 Question 86 Discussion:
Question #: 86
Topic #: 9

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project Management process are you working with when you create a new target schedule?


A.

Develop schedule


B.

Estimate activity durations


C.

Control schedule


D.

Estimate activity resources


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.