Pass the PMI PMI Certification PMI-SP Questions and answers with CertsForce

Viewing page 1 out of 10 pages
Viewing questions 1-10 out of questions
Questions # 1:

George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?

Options:

A.

.96


B.

-$77,800


C.

$-34,500


D.

-$13,800


Expert Solution
Questions # 2:

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

Options:

A.

Scope Verification


B.

Configuration Management System


C.

Project Management Information System


D.

Integrated Change Control


Expert Solution
Questions # 3:

Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not approve of this and warns Jim of Parkinson's Law. What is Parkinson's Law?

Options:

A.

People will behave based on what their behavior brings them.


B.

As employees do repetitive tasks, duration should decrease.


C.

Work expands to fill the amount of time allotted to it.


D.

An exponential increase labor does not correlate to an exponential decrease in duration.


Expert Solution
Questions # 4:

Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?

Options:

A.

140


B.

10


C.

325


D.

5


Expert Solution
Questions # 5:

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

Options:

A.

Cost variance report


B.

Exceptions report


C.

Performance management report


D.

Schedule variance report


Expert Solution
Questions # 6:

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

Options:

A.

Project calendar


B.

Resource calendar


C.

Organizational calendar


D.

Company calendar


Expert Solution
Questions # 7:

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?

Options:

A.

Estimate activity durations


B.

Estimate activity resources


C.

Control schedule


D.

Develop schedule


Expert Solution
Questions # 8:

You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never worked with the technology, as is in this project. During the define activities process, you rely on your project team and two consultants to coach you and identify the type of activities the project will include. Which tool and technique are you using in the define activities process in this scenario?

Options:

A.

Templates


B.

Rolling wave planning


C.

Decomposition


D.

Expert judgment


Expert Solution
Questions # 9:

You are the project manager for your organization. You need the oak cabinets for your project delivered by December 1 in order to install the floors around the oak cabinets by December 15. Your company's procurement office generally takes 45 days to complete procurement orders. Based on this information, how should you schedule the lead time for the cabinet delivery?

Options:

A.

Cabinet procurement December 1, plus 45 days lead time


B.

Cabinet procurement November 15


C.

Cabinet procurement December 1, minus 45 days lead time


D.

Cabinet procurement December 15 minus 45 days lead time


Expert Solution
Questions # 10:

You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you'll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project's current cost performance index (CPI) is. What value should you report to management based on your project's performance?

Options:

A.

$306,000


B.

.94


C.

$344,250


D.

.75


Expert Solution
Viewing page 1 out of 10 pages
Viewing questions 1-10 out of questions