PMI Scheduling Professional PMI-SP Question # 2 Topic 1 Discussion

PMI Scheduling Professional PMI-SP Question # 2 Topic 1 Discussion

PMI-SP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?


A.

Scope Verification


B.

Configuration Management System


C.

Project Management Information System


D.

Integrated Change Control


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.