Question #: 2
Topic #: 1

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?


A.

Scope Verification


B.

Configuration Management System


C.

Project Management Information System


D.

Integrated Change Control