PMI Scheduling Professional PMI-SP Question # 8 Topic 1 Discussion

PMI Scheduling Professional PMI-SP Question # 8 Topic 1 Discussion

PMI-SP Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never worked with the technology, as is in this project. During the define activities process, you rely on your project team and two consultants to coach you and identify the type of activities the project will include. Which tool and technique are you using in the define activities process in this scenario?


A.

Templates


B.

Rolling wave planning


C.

Decomposition


D.

Expert judgment