PMI Scheduling Professional PMI-SP Question # 7 Topic 1 Discussion

PMI Scheduling Professional PMI-SP Question # 7 Topic 1 Discussion

PMI-SP Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?


A.

Estimate activity durations


B.

Estimate activity resources


C.

Control schedule


D.

Develop schedule