PMI Scheduling Professional PMI-SP Question # 9 Topic 1 Discussion

PMI Scheduling Professional PMI-SP Question # 9 Topic 1 Discussion

PMI-SP Exam Topic 1 Question 9 Discussion:
Question #: 9
Topic #: 1

You are the project manager for your organization. You need the oak cabinets for your project delivered by December 1 in order to install the floors around the oak cabinets by December 15. Your company's procurement office generally takes 45 days to complete procurement orders. Based on this information, how should you schedule the lead time for the cabinet delivery?


A.

Cabinet procurement December 1, plus 45 days lead time


B.

Cabinet procurement November 15


C.

Cabinet procurement December 1, minus 45 days lead time


D.

Cabinet procurement December 15 minus 45 days lead time