PMI Scheduling Professional PMI-SP Question # 5 Topic 1 Discussion

PMI Scheduling Professional PMI-SP Question # 5 Topic 1 Discussion

PMI-SP Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?


A.

Cost variance report


B.

Exceptions report


C.

Performance management report


D.

Schedule variance report