PMI Scheduling Professional PMI-SP Question # 85 Topic 9 Discussion

PMI Scheduling Professional PMI-SP Question # 85 Topic 9 Discussion

PMI-SP Exam Topic 9 Question 85 Discussion:
Question #: 85
Topic #: 9

You are the project manager of the NHQ Project. This project has a Budget at Completion of $750,000 and is expected to take 18 months to complete. The project is supposed to be 75 percent complete, but due to some errors the project is only 60 percent complete. At this time the project has spent $465,500. Management has asked you to review the project work and report the project's SPI. What is the SPI for this project?


A.

0.97


B.

0.80


C.

$562,500


D.

-$112,500