PMI Scheduling Professional PMI-SP Question # 84 Topic 9 Discussion

PMI Scheduling Professional PMI-SP Question # 84 Topic 9 Discussion

PMI-SP Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?


A.

-$98,217.78


B.

-$44,198


C.

$441,025.64


D.

$243,219.78