PMI-SP Exam Topic 9 Question 87 Discussion:
Question #: 87
Topic #: 9

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?


A.

Resource competition


B.

Matrix organization


C.

Resource requirement


D.

Resource constraint