PMI Scheduling Professional PMI-SP Question # 88 Topic 9 Discussion

PMI Scheduling Professional PMI-SP Question # 88 Topic 9 Discussion

PMI-SP Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

You are the project manager of the NGG Project. This project will be using a new material that the project team has never worked with before. You'd like to use some preventive action to ensure that the installation of the new materials is successful in the project. Which one of the following project actions is an example of the best preventive action for this project?


A.

Hire a subject matter expert to train the project team how to install the materials.


B.

Purchase additional materials so in case the team wastes materials during their installation.


C.

Hire a subject matter expert to install the new materials.


D.

Create incentive by rewarding the project team if they don't waste the materials.