Pass the PMI PMI Certification PMI-SP Questions and answers with CertsForce

Viewing page 2 out of 10 pages
Viewing questions 11-20 out of questions
Questions # 11:

You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?

Options:

A.

Increase the duration estimates for each activity.


B.

Discipline the project team.


C.

Add management reserve.


D.

Corrective actions.


Expert Solution
Questions # 12:

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

Options:

A.

$142,000


B.

$232,000


C.

$41,750


D.

$23,750


Expert Solution
Questions # 13:

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

Options:

A.

Work performance information


B.

Change requests


C.

Work performance measurements


D.

Forecasting method


Expert Solution
Questions # 14:

You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?

Options:

A.

Preventive action


B.

Defect repair validation


C.

Implemented corrective action


D.

Quality control


Expert Solution
Questions # 15:

You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, the project sponsor, and ten members of your project team. What type of communication method are you using in this instance?

Options:

A.

Interactive communication


B.

Active communication


C.

Pull technique


D.

Push technique


Expert Solution
Questions # 16:

Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

Options:

A.

Precedence Diagramming Method


B.

Schedule network template


C.

Dependency determination


D.

Activity on the Node


Expert Solution
Questions # 17:

You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are able to get their deliveries on time. Which type of scheduling would be required in such a scenario?

Options:

A.

Critical path scheduling


B.

Time-oriented scheduling


C.

Resource-oriented scheduling


D.

Network scheduling


Expert Solution
Questions # 18:

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint


B.

Assumption


C.

Execution variance analysis


D.

Resource leveling heuristic


Expert Solution
Questions # 19:

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:

A.

-$135,000


B.

.67


C.

.81


D.

-$65,000


Expert Solution
Questions # 20:

Which of the following statements best describes an activity in a project?

Options:

A.

It is a defined set of functions a resource must complete for the project scope to be considered complete.


B.

It is the effort needed to complete a work package.


C.

It is the unit of resource utilization needed to complete a project deliverable.


D.

It is a listing of all project work that must be accomplished for the project scope to be considered complete.


Expert Solution
Viewing page 2 out of 10 pages
Viewing questions 11-20 out of questions