Questions # 21:

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

Options:

A.

Quality inspections and compliance


B.

Location, logistics, and resource availability analysis


C.

Labor productivity studies from previous similar projects in the area


D.

The average price of general labor in the area


Expert Solution
Questions # 22:

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?

Options:

A.

1.07


B.

0.98


C.

0.89


D.

Ten percent


Expert Solution
Questions # 23:

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

Options:

A.

It is a term used to describe activities whose effort cannot be directly measured to the project objectives.


B.

It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.


C.

It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.


D.

It is a term used to describe activities that are core project management processes, but not core project activities.


Expert Solution
Questions # 24:

You are the project manager of the NHG. The following figure represents your project network diagram.

Question # 24

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

Options:

A.

The critical path will now take 26 days.


B.

The critical path will now take 17 days.


C.

The critical path will now take 23 days.


D.

The critical path will now take 20 days.


Expert Solution
Questions # 25:

You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?

Options:

A.

Project calendar


B.

Project constraints


C.

Project objectives


D.

Project management plan


Expert Solution
Questions # 26:

Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?

Options:

A.

It is not good news because a larger number means the schedule duration estimates were likely to be wrong to begin with.


B.

They likely do not understand the SPI formula.


C.

It is not good news, as the number should be closer to 100 than 0.


D.

It is good news, but Mark may have large cost variances to achieve this value.


Expert Solution
Questions # 27:

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

Options:

A.

$122,845


B.

-$51,000


C.

-$85,000


D.

Zero


Expert Solution
Questions # 28:

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

Options:

A.

1.02


B.

0.98


C.

0.90


D.

-$108,120


Expert Solution
Questions # 29:

Jack works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should Jack tell the management?

Options:

A.

$1,087,497.74


B.

$755,000.56


C.

$1,112,978.45


D.

$790,988.76


Expert Solution
Questions # 30:

Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that Harry will need to report to management?

Options:

A.

$1,312,504


B.

$787,504


C.

$1,812,498


D.

$725,000


Expert Solution