Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.


A.

Quality inspections and compliance


B.

Location, logistics, and resource availability analysis


C.

Labor productivity studies from previous similar projects in the area


D.

The average price of general labor in the area