PMI Scheduling Professional PMI-SP Question # 26 Topic 3 Discussion

PMI Scheduling Professional PMI-SP Question # 26 Topic 3 Discussion

PMI-SP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?


A.

It is not good news because a larger number means the schedule duration estimates were likely to be wrong to begin with.


B.

They likely do not understand the SPI formula.


C.

It is not good news, as the number should be closer to 100 than 0.


D.

It is good news, but Mark may have large cost variances to achieve this value.


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.