PMI-SP Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?


A.

Project calendar


B.

Project constraints


C.

Project objectives


D.

Project management plan