You are the project manager of the NHG. The following figure represents your project network diagram.

PMI-SP Question 24

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?


A.

The critical path will now take 26 days.


B.

The critical path will now take 17 days.


C.

The critical path will now take 23 days.


D.

The critical path will now take 20 days.