PMI Scheduling Professional PMI-SP Question # 23 Topic 3 Discussion

PMI Scheduling Professional PMI-SP Question # 23 Topic 3 Discussion

PMI-SP Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?


A.

It is a term used to describe activities whose effort cannot be directly measured to the project objectives.


B.

It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.


C.

It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.


D.

It is a term used to describe activities that are core project management processes, but not core project activities.