New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Scheduling Professional PMI-SP Question # 29 Topic 3 Discussion

PMI Scheduling Professional PMI-SP Question # 29 Topic 3 Discussion

PMI-SP Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

Jack works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should Jack tell the management?


A.

$1,087,497.74


B.

$755,000.56


C.

$1,112,978.45


D.

$790,988.76


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.