PMI Scheduling Professional PMI-SP Question # 30 Topic 4 Discussion

PMI Scheduling Professional PMI-SP Question # 30 Topic 4 Discussion

PMI-SP Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that Harry will need to report to management?


A.

$1,312,504


B.

$787,504


C.

$1,812,498


D.

$725,000


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.