Questions # 51:

Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?

Options:

A.

Project calendar


B.

Activity attributes


C.

Resource calendar


D.

Schedule management plan


Expert Solution
Questions # 52:

You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?

Options:

A.

Project scope statement


B.

Project schedule network diagram


C.

Activity list


D.

Organizational process assets


Expert Solution
Questions # 53:

Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project - including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?

Options:

A.

Expert judgment


B.

Analogous estimate


C.

Templates


D.

Parametric estimate


Expert Solution
Questions # 54:

You work as a project manager for BlueWell Inc. Which of the following tools/techniques will you use to demonstrate how a process behaves over time, and when a process is subject to special cause variation, resulting in an out-of-control condition?

Options:

A.

Pareto Chart


B.

Ishikawa Diagram


C.

Scatter Chart


D.

Control Chart


Expert Solution
Questions # 55:

Which of the following group activity techniques allows a large number of ideas to be sorted into groups for review and analysis?

Options:

A.

Idea/mind mapping


B.

Nominal group technique


C.

Delphi technique


D.

Affinity diagram


Expert Solution
Questions # 56:

Sam works as a project manager for BlueWell Inc. Which of the following processes will he use for selecting a scheduling method, scheduling tool, incorporating project specific data within that scheduling tool to develop a project specific schedule model, and generating project schedule?

Options:

A.

Constructability Analysis process


B.

Schedule Maintenance process


C.

Schedule Development process


D.

Perform Integrated Change Control process


Expert Solution
Questions # 57:

Andy is the project manager of the NHGQ project for his organization. He has elected to use a three-point estimate for his project. His project team, however, is complaining about participating in this estimate type because of the time it takes to predict the duration of activities. Andy, as the project manager, tells the project team that they must create the time estimate, as it will help this project and future similar projects. What is a three-point estimate?

Options:

A.

Each activity must be estimated for its optimistic, pessimistic, and most likely duration.


B.

Each activity must be estimated for its optimistic, pessimistic, and most likely duration and then an average for the estimate is created.


C.

A three-point estimate, also known as PERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.


D.

A three-point estimate, also known as GERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.


Expert Solution
Questions # 58:

You are the project manager of the NDF project. You need to determine how often a complete project report can be made, including forecasted project completion information for your project. How often should the report be created?

Options:

A.

Weekly


B.

One per status milestone reached


C.

Regularly or on an exception basis


D.

Exception-by-exception basis


Expert Solution
Questions # 59:

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

Options:

A.

Contract


B.

Reserve analysis


C.

Scope baseline


D.

Project schedule


Expert Solution
Questions # 60:

You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems in your project. Based on your planning for monitoring and controlling project performance, you know that there are three outputs of performance reporting. Which one of the following is the only output that is most appropriate for this poorly performing project?

Options:

A.

Organizational process assets update


B.

Performance reports


C.

Performance re-baselining


D.

Change requests


Expert Solution