PMI Scheduling Professional PMI-SP Question # 58 Topic 6 Discussion

PMI Scheduling Professional PMI-SP Question # 58 Topic 6 Discussion

PMI-SP Exam Topic 6 Question 58 Discussion:
Question #: 58
Topic #: 6

You are the project manager of the NDF project. You need to determine how often a complete project report can be made, including forecasted project completion information for your project. How often should the report be created?


A.

Weekly


B.

One per status milestone reached


C.

Regularly or on an exception basis


D.

Exception-by-exception basis


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.