PMI Scheduling Professional PMI-SP Question # 53 Topic 6 Discussion

PMI Scheduling Professional PMI-SP Question # 53 Topic 6 Discussion

PMI-SP Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project - including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?


A.

Expert judgment


B.

Analogous estimate


C.

Templates


D.

Parametric estimate


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.