PMI-SP Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?


A.

Project scope statement


B.

Project schedule network diagram


C.

Activity list


D.

Organizational process assets