Questions # 61:

Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are perfect. The only thing left to in the project is to verify scope. This process will be performed by the project stakeholders. Maurice is required to submit a final project report and report on the project performance. Maurice's project had a budget of $234,000 but the project spent $245,000. In the final report management wants to know the project's cost performance index (CPI). What value should Maurice report?

Options:

A.

-$11,000


B.

.96


C.

There is not enough information to know.


D.

1


Expert Solution
Questions # 62:

What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?

Options:

A.

Judgmental methods


B.

Time series method


C.

Ensemble forecasting


D.

Causal/econometric method


Expert Solution
Questions # 63:

You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within the project scope. What process must you and the project team complete next in this scenario?

Options:

A.

Create the activity list.


B.

Create the WBS.


C.

Create the risk assessment.


D.

Determine the project budget.


Expert Solution
Questions # 64:

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 90 percent done by this date. She has spent $490,000 to date. What should Billy report as her cost performance index (CPI)for this project?

Options:

A.

.07


B.

1.07


C.

$34,000


D.

.89


Expert Solution
Questions # 65:

You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?

Options:

A.

Amount of buffer remaining to the amount of resources available


B.

Amount of buffer remaining to the amount of buffer used


C.

Availability of project resources and project buffer


D.

Amount of buffer needed to the amount of buffer remaining


Expert Solution
Questions # 66:

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.

Project change control process


B.

Perform integrated change control process


C.

Configuration management


D.

Communications management


Expert Solution
Questions # 67:

Which of the following provides a method to track project progress during project execution against what was planned?

Options:

A.

Team members profile


B.

Benefit-cost ratio


C.

Schedule baseline


D.

Detailed project budget


Expert Solution
Questions # 68:

If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?

Options:

A.

You have added lag time to the project activities.


B.

You have added management reserve to the project activities.


C.

You have added lead time to the project activities.


D.

You have added float to the project activities.


Expert Solution
Questions # 69:

Kay is the project manager of the QUI Project. This project is done but is also considerably over budget. Kay has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Kay do with the information regarding the schedule delays and cost overruns?

Options:

A.

Create an entry in the lessons learned documentation and explain her reasoning behind the corrective actions.


B.

Create an exceptions report.


C.

Create a variance report.


D.

File the information as part of the project final report.


Expert Solution
Questions # 70:

Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not exceed 25 hours per week. Ned's pay is based on how quickly he can complete the project work. What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?

Options:

A.

Crash the project.


B.

Add more risk mitigation.


C.

Reduce the amount of labor.


D.

Reduce the project scope.


Expert Solution