Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are perfect. The only thing left to in the project is to verify scope. This process will be performed by the project stakeholders. Maurice is required to submit a final project report and report on the project performance. Maurice's project had a budget of $234,000 but the project spent $245,000. In the final report management wants to know the project's cost performance index (CPI). What value should Maurice report?
What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?
You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within the project scope. What process must you and the project team complete next in this scenario?
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 90 percent done by this date. She has spent $490,000 to date. What should Billy report as her cost performance index (CPI)for this project?
You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?
You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?
Which of the following provides a method to track project progress during project execution against what was planned?
If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?
Kay is the project manager of the QUI Project. This project is done but is also considerably over budget. Kay has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Kay do with the information regarding the schedule delays and cost overruns?
Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not exceed 25 hours per week. Ned's pay is based on how quickly he can complete the project work. What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?