A schedule baseline provides a method to track project progress during project execution against what was planned. What is schedule baseline? Schedule baseline is a project schedule used in measuring project progress. It helps provide a comparison with the actual progress of work against the schedule and to determine if performance to date is within acceptable parameters. Any change caused by change in scope of the project invalidates the original schedule and requires a new baseline schedule.
Answer options D, A, and B are incorrect. A detailed project budget, team members profile, and benefit-cost ratio will not help you track project progress. What is BCR? A benefit-cost ratio (BCR) is an indicator, used in the formal discipline of cost-benefit analysis, that attempts to summarize the overall value for money of a project or proposal. A BCR is the ratio of the benefits of a project or proposal, expressed in monetary terms, relative to its costs, also expressed in monetary terms. All benefits and costs should be expressed in discounted present values. For e.g., a BCR of $3.8 indicates a payback of $3.8 for each dollar expended.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit