PMI Scheduling Professional PMI-SP Question # 67 Topic 7 Discussion

PMI Scheduling Professional PMI-SP Question # 67 Topic 7 Discussion

PMI-SP Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

Which of the following provides a method to track project progress during project execution against what was planned?


A.

Team members profile


B.

Benefit-cost ratio


C.

Schedule baseline


D.

Detailed project budget


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.