PMI Scheduling Professional PMI-SP Question # 68 Topic 7 Discussion

PMI Scheduling Professional PMI-SP Question # 68 Topic 7 Discussion

PMI-SP Exam Topic 7 Question 68 Discussion:
Question #: 68
Topic #: 7

If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?


A.

You have added lag time to the project activities.


B.

You have added management reserve to the project activities.


C.

You have added lead time to the project activities.


D.

You have added float to the project activities.


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.