Question #: 69
Topic #: 7

Kay is the project manager of the QUI Project. This project is done but is also considerably over budget. Kay has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Kay do with the information regarding the schedule delays and cost overruns?


A.

Create an entry in the lessons learned documentation and explain her reasoning behind the corrective actions.


B.

Create an exceptions report.


C.

Create a variance report.


D.

File the information as part of the project final report.