Question #: 70
Topic #: 8

Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not exceed 25 hours per week. Ned's pay is based on how quickly he can complete the project work. What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?


A.

Crash the project.


B.

Add more risk mitigation.


C.

Reduce the amount of labor.


D.

Reduce the project scope.