PMI Scheduling Professional PMI-SP Question # 71 Topic 8 Discussion

PMI Scheduling Professional PMI-SP Question # 71 Topic 8 Discussion

PMI-SP Exam Topic 8 Question 71 Discussion:
Question #: 71
Topic #: 8

You are the project manager for your organization. You are working with your project team to define the project network diagram. Several of the activities in the project schedule appear to have external constraints. Who among the following determines which dependencies are external to the project?


A.

Project team


B.

Project sponsor


C.

Project manager


D.

Project management team


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.