PMI-SP Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?


A.

Expert judgment


B.

Project charter


C.

Stakeholder analysis


D.

Stakeholder register