PMI Scheduling Professional PMI-SP Question # 62 Topic 7 Discussion

PMI Scheduling Professional PMI-SP Question # 62 Topic 7 Discussion

PMI-SP Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?


A.

Judgmental methods


B.

Time series method


C.

Ensemble forecasting


D.

Causal/econometric method