You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?


A.

Amount of buffer remaining to the amount of resources available


B.

Amount of buffer remaining to the amount of buffer used


C.

Availability of project resources and project buffer


D.

Amount of buffer needed to the amount of buffer remaining