Questions # 41:

You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:

Question # 41

Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

Options:

A.

32 days


B.

29 days


C.

27 days


D.

26 days


Expert Solution
Questions # 42:

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance index based on the current BAC?

Options:

A.

1.02


B.

0.010


C.

0.75


D.

0.95


Expert Solution
Questions # 43:

You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?

Options:

A.

The duration will increase, but the labor will stay the same.


B.

The duration will decrease as new team members are brought onto the project.


C.

Nothing, new resources will be incorporated into the project team.


D.

The duration will increase, but the labor will decrease.


Expert Solution
Questions # 44:

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

Question # 44
Options:

A.

Static


B.

Deterrent


C.

Noise


D.

Barrier


Expert Solution
Questions # 45:

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?

Options:

A.

$176,675


B.

$122,845


C.

-$85,000


D.

-$51,000


Expert Solution
Questions # 46:

The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

Options:

A.

Activity list


B.

Milestone list


C.

Activity attributes


D.

Project document updates


Expert Solution
Questions # 47:

You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?

Options:

A.

48


B.

20o, 45m, 90p


C.

90


D.

45


Expert Solution
Questions # 48:

Examine the figure given below: Which path is considered the critical path?

Options:

A.

ACDFJ


B.

ACGIJ


C.

ABEFJ


D.

ABDFJ


Expert Solution
Questions # 49:

You are the project manager for your organization. Maagement has asked you for this current project. You use the critical chain method to create the project network diagram rather than the more traditional critical path method. What is the critical chain method?

Options:

A.

It examines only the non-critical path activities that are considered near critical, if the float is one day or less.


B.

It examines only the critical path activities to determine when the project completion date may be.


C.

It examines the availability of needed project resources to determine when activities may actually happen.


D.

It generates a Gantt chart that reflects the availability of project resources and considers working and non-working days for the project.


Expert Solution
Questions # 50:

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?

Options:

A.

$163,626


B.

$130,901


C.

-$985,040


D.

0.16


Expert Solution