Question #: 50
Topic #: 6

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?


A.

$163,626


B.

$130,901


C.

-$985,040


D.

0.16