Question #: 49
Topic #: 5

You are the project manager for your organization. Maagement has asked you for this current project. You use the critical chain method to create the project network diagram rather than the more traditional critical path method. What is the critical chain method?


A.

It examines only the non-critical path activities that are considered near critical, if the float is one day or less.


B.

It examines only the critical path activities to determine when the project completion date may be.


C.

It examines the availability of needed project resources to determine when activities may actually happen.


D.

It generates a Gantt chart that reflects the availability of project resources and considers working and non-working days for the project.