PMI Scheduling Professional PMI-SP Question # 45 Topic 5 Discussion

PMI Scheduling Professional PMI-SP Question # 45 Topic 5 Discussion

PMI-SP Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?


A.

$176,675


B.

$122,845


C.

-$85,000


D.

-$51,000