Question #: 43
Topic #: 5

You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?


A.

The duration will increase, but the labor will stay the same.


B.

The duration will decrease as new team members are brought onto the project.


C.

Nothing, new resources will be incorporated into the project team.


D.

The duration will increase, but the labor will decrease.