PMI Scheduling Professional PMI-SP Question # 42 Topic 5 Discussion

PMI Scheduling Professional PMI-SP Question # 42 Topic 5 Discussion

PMI-SP Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance index based on the current BAC?


A.

1.02


B.

0.010


C.

0.75


D.

0.95