PMI Scheduling Professional PMI-SP Question # 47 Topic 5 Discussion

PMI Scheduling Professional PMI-SP Question # 47 Topic 5 Discussion

PMI-SP Exam Topic 5 Question 47 Discussion:
Question #: 47
Topic #: 5

You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?


A.

48


B.

20o, 45m, 90p


C.

90


D.

45


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.