Questions # 31:

Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?

Options:

A.

Project charter


B.

Scope of statement


C.

SOW


D.

WBS


Expert Solution
Questions # 32:

John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the importance of communication in the project. He would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

Options:

A.

3000


B.

79


C.

80


D.

3160


Expert Solution
Questions # 33:

Examine the figure given below:

Question # 33

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

Options:

A.

Three days


B.

One day


C.

Four days


D.

Zero days


Expert Solution
Questions # 34:

Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his guidance. You, a team leader of a project, inform Fredrick about the performance indexes of your project. The schedule performance index (SPI) of your project is 1.325. What does this figure indicate?

Options:

A.

The schedule performance is better than expected.


B.

The schedule performance is right on target.


C.

The cost performance is better than expected.


D.

The schedule performance is below expectation.


Expert Solution
Questions # 35:

Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?

Options:

A.

Communications management plan


B.

Stakeholder register


C.

Requirements


D.

Stakeholder management strategy


Expert Solution
Questions # 36:

You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?

Options:

A.

Project Human Resources Management Plan


B.

Project Staffing Management Plan


C.

Project Communications Management Plan


D.

Project Schedule Management Plan


Expert Solution
Questions # 37:

Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?

Options:

A.

Idea/mind mapping


B.

Delphi technique


C.

Nominal group technique


D.

Affinity diagram


Expert Solution
Questions # 38:

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

Options:

A.

Resource calendars


B.

Schedule data


C.

Activity list


D.

Project scope statement


Expert Solution
Questions # 39:

You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?

Options:

A.

(O+ML+P)


B.

(O+(6M)+P)6


C.

(O+ML+P)/3


D.

(O+(4M)+P)/6


Expert Solution
Questions # 40:

You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?

Options:

A.

Parametric estimate


B.

Definitive estimate


C.

Analogous estimate


D.

Bottom-up estimate


Expert Solution