PMI Scheduling Professional PMI-SP Question # 33 Topic 4 Discussion

PMI Scheduling Professional PMI-SP Question # 33 Topic 4 Discussion

PMI-SP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

Examine the figure given below:

PMI-SP Question 33

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?


A.

Three days


B.

One day


C.

Four days


D.

Zero days


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.