PMI-SP Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the importance of communication in the project. He would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?


A.

3000


B.

79


C.

80


D.

3160