Question #: 34
Topic #: 4

Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his guidance. You, a team leader of a project, inform Fredrick about the performance indexes of your project. The schedule performance index (SPI) of your project is 1.325. What does this figure indicate?


A.

The schedule performance is better than expected.


B.

The schedule performance is right on target.


C.

The cost performance is better than expected.


D.

The schedule performance is below expectation.