Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Scheduling Professional PMI-SP Question # 39 Topic 4 Discussion

PMI Scheduling Professional PMI-SP Question # 39 Topic 4 Discussion

PMI-SP Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?


A.

(O+ML+P)


B.

(O+(6M)+P)6


C.

(O+ML+P)/3


D.

(O+(4M)+P)/6


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.