PMI Scheduling Professional PMI-SP Question # 40 Topic 5 Discussion

PMI Scheduling Professional PMI-SP Question # 40 Topic 5 Discussion

PMI-SP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?


A.

Parametric estimate


B.

Definitive estimate


C.

Analogous estimate


D.

Bottom-up estimate


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.