PMI-SP Exam Topic 7 Question 60 Discussion:
Question #: 60
Topic #: 7

You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems in your project. Based on your planning for monitoring and controlling project performance, you know that there are three outputs of performance reporting. Which one of the following is the only output that is most appropriate for this poorly performing project?


A.

Organizational process assets update


B.

Performance reports


C.

Performance re-baselining


D.

Change requests