Question #: 13
Topic #: 2

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?


A.

Work performance information


B.

Change requests


C.

Work performance measurements


D.

Forecasting method