PMI Scheduling Professional PMI-SP Question # 12 Topic 2 Discussion

PMI Scheduling Professional PMI-SP Question # 12 Topic 2 Discussion

PMI-SP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?


A.

$142,000


B.

$232,000


C.

$41,750


D.

$23,750


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.